Belgian authorities have ordered Google to stop construction on a nearly completed data center in southern Belgium after inspectors discovered that work had continued despite the revocation of its amended building permit.
Regional officials issued the stop-work order on November 26 at the construction site in Aiseau-Presles, near Charleroi. Approximately 300 workers were present when inspectors visited the facility.
The disputed building covers about 7.4 acres within a business park developed on the site of a former coal mine. Officials found that its main structural work had already been completed.
Regional government spokesperson Nicolas Yernaux said on Friday that a report alleging unauthorized construction was being submitted to public prosecutors.
Google’s revised plans raised concerns over water consumption

Google originally received planning permission in 2024 to construct three smaller data centers using air-based cooling systems.
In 2025, the company applied to combine two of the planned buildings into a larger facility and replace the original cooling system with one that would use water from the nearby Sambre River.
Under the revised proposal, the facility would draw approximately 600 cubic meters of river water per hour.
Regional authorities initially approved the amended plans in April 2026. However, local residents and environmental groups challenged the decision, raising concerns about water availability and the potential impact of drought.
Wallonia’s infrastructure minister, François Desquesnes, revoked the amended permit in August.
While the original construction permit remains valid, Google has appealed the decision rejecting its revised plans. Belgium’s Council of State is scheduled to hold a hearing on January 7, 2027.
Greenpeace investigation prompted action

Environmental organization Greenpeace Belgium had raised concerns that construction was continuing despite the August decision.
Earlier this week, the group presented evidence of ongoing construction and submitted an emergency request asking regional authorities to intervene.
Greenpeace welcomed the construction halt in a statement on November 27, describing it as a positive development for local residents and the environment.
Google confirmed that it had stopped construction in accordance with instructions from local authorities. The company also reaffirmed its commitment to complying with Belgian laws and cooperating with regional officials.
Google faces growing environmental scrutiny in Europe
The dispute comes as major technology companies expand their data center infrastructure to support growing demand for artificial intelligence and cloud computing services.
Google is facing similar environmental scrutiny in Finland, where authorities launched a criminal investigation in October into possible environmental violations connected to another planned data center.
Construction on the disputed Belgian facility remains on hold as Google awaits further guidance from regional authorities and the outcome of its legal appeal.